How to Use This Blog

Please scan though the postings and if you desire to comment please do. On the lower left side you will find a listing of all the postings broken down into year and month. If you select a year the entire posts from that year will be available for your viewing. If you desire to enlarge any picture -- just double click the given picture embedded within the text for better viewing.

Friday, August 3, 2012

Still Working Projects

Yesterday we finished up the softening of the removed bunker behind 4's green and started work on the removed bunker behind 6's green.  Our plan is to finish that bunker today and maybe get started on the removed bunker in the right back of 2's green.  We will wait to see how the progress is going on 6 before that can be determined.
4's Back Removed Bunker After Softened
The driving tee expansion is for the most part level to the best of our abilities given our equipment we have.  Yesterday the raising of the irrigation heads and valve boxes began to reach the new level to the tee, and today hopefully we will finish the irrigation.  If all goes well today Monday we will sprig this area and begin the roller base irrigation to grow the turf back in time for overseeding.
8's ADA Cart Path Work
The ADA access curb removal along 8 and behind 7's green is almost complete.  Today we will finish all of the concrete removal and begin the framing for next week's concrete pouring.  We have roped these entrances off to protect our membership but still care should be observed around these regions until the concrete work has been completed.  Lastly, it was requested and approved to remove the citrus tree that has been dying next to 11's tee ... we are doing that today.
11's Tee Tree Slated for Removal
On the course we are topdressing and fertilizing the greens.  With these weekly topdressings the greens will continue to improve in their playability.

No comments:

Post a Comment