One of 8's Curbing Repair |
Yesterday, we finished removing the broken curbing along 8's green and re-poured and shaped the new curb back into it's place. Today, was the coldest of the year so far -- 31 degrees on the golf course. And of course, today was the first ladies member/guest day to boot. Working with the ladies by skipping the mowing of the greens we were able to get everything else prepped with only a 30 minute delay. This was pretty good considering at 8:30 we still had hard frost in numerous areas.
|
Start of the Install of the Drain in the Big Bed |
With the frost delay we were able to start on the clubhouse's big bed project. The first phase includes opening along the wall so we can waterproof that backside of it to prevent seepage. Additionally. the two trees were removed and the stumps were ground.
|
Grinding the Stumps of the Removed Tree in the Big Bed |
In addition to this drainage work we start installing the second tier's irrigation above where the animal's were to be able to finally finish the project we started almost two years ago.
|
Joesph Working on Irrigation on the Second Tier |