We have started several smaller projects such as re-shaping of 2 and 6's greenside bunkers and adding much needed drains around the course. These projects are mostly finished and should be healed in a couple of weeks. In addition, all roped off areas are out of play due to potential damage to the turf. We have also opened up the area which is always wet along the right side of 2 from the drainage of the streets. This area will be repaired soon.
You may have noticed that there is a crane out on 18 next to the well. This crane has just removed our pump and shaft which required repair to the lowering of the water table in the Valley. Over the past 5 years the water table has dropped 30 ft and since 1995 almost 100 ft. The repairs on the shaft will be completed on Thursday, however, on Friday the crane will be removing the shaft and pump on 6's well since it too has been having issues and is currently blowing out water from the top of the shaft into the motor. This entire project will be completed in a couple of weeks.